CHEC Company Says It Can’t Build At A Loss

Paying the bills

Latest

Can Microdose Mushrooms Boost Productivity? Find Out What Experts Are Saying

Microdosing involves taking a small, controlled amount—usually around 1/8...

“Respect for the division of powers” legislator tells President Chaves

QCOSTARICA - A call for respect for the division...

Carlos Alvarado: Populism is thriving in Costa Rica

QCOSTARICA -- On Wednesday, former president Carlos Alvarado (2018-2022),...

1960s Costa Rica

QCOSTARICA - The first indigenous peoples of Costa Rica...

Holidays left in 2024

QCOSTARICA -- Costa Rica just came off a long...

Costa Rica will not receive African migrants

QCOSTARICA -- Costa Rica's President, Rodrigo Chaves, stated on...

Dollar Exchange

¢497.92 BUY

¢504.11 SELL

18 April 2024 - At The Banks - Source: BCCR

Paying the bills

Share

201504282134491.pag8

QCOSTARICA – Representatives of the Chinese construction company, CHEC, awarded the contract to expand the Ruta 32 (San José – Limon) road, says the work comes out at a higher cost than initially agreed with the government.

“We want this road to be good for all and are willing to cooperate, we could do it without a profit, but cannot at a loss,” said Teresa Wu, company representative.

- Advertisement -

Wu explained that to meet all the technical requirements requested by the current government of Costa Rica, the cost would be higher than the initial US$395 million dollars agreed to with the previous administration.

The company estimates the additional costs at US$90 million dollars, not taking into account expropriations and relocations of public services.

The higher cost is based on draft comments by the Ministerio de Obras Publicas y Transportes (MOPT), improving bridges and pedestrian overpasses.

“They are asking for more and new standards that are outside the scope of the project. The result means an increase in cost because it will require more material and use of more machinery. It’s like you’re asked to build a three-story house and then expect four,” Wu said.

The expansion of the road, some 107 kilometres between Limon and the Rio Frio crossing is expected to start next year, but will depend on the government being satisfied with the designs submitted and expropriations concluded.

The work will be financed by a loan from the Chinese government, which was approved by the Legislative Assembly, with the understanding that the cost would not increase despite the improvements requested.

- Advertisement -

Source: Larepublica.net

- Advertisement -
Paying the bills
Rico
Ricohttp://www.theqmedia.com
"Rico" is the crazy mind behind the Q media websites, a series of online magazines where everything is Q! In these times of new normal, stay at home. Stay safe. Stay healthy.

Related Articles

Carlos Alvarado: Populism is thriving in Costa Rica

QCOSTARICA -- On Wednesday, former president Carlos Alvarado (2018-2022), said he...

1960s Costa Rica

QCOSTARICA - The first indigenous peoples of Costa Rica were hunters...

Subscribe to our stories

To be updated with all the latest news, offers and special announcements.

Discover more from Q COSTA RICA

Subscribe now to keep reading and get access to the full archive.

Continue reading