China Expects A One-year Delay In Construction Of Road To Limon

Paying the bills

Latest

Can Microdose Mushrooms Boost Productivity? Find Out What Experts Are Saying

Microdosing involves taking a small, controlled amount—usually around 1/8...

“Respect for the division of powers” legislator tells President Chaves

QCOSTARICA - A call for respect for the division...

Carlos Alvarado: Populism is thriving in Costa Rica

QCOSTARICA -- On Wednesday, former president Carlos Alvarado (2018-2022),...

1960s Costa Rica

QCOSTARICA - The first indigenous peoples of Costa Rica...

Holidays left in 2024

QCOSTARICA -- Costa Rica just came off a long...

Costa Rica will not receive African migrants

QCOSTARICA -- Costa Rica's President, Rodrigo Chaves, stated on...

Dollar Exchange

¢497.92 BUY

¢504.11 SELL

18 April 2024 - At The Banks - Source: BCCR

Paying the bills

Share

The 345-meter-long bridge over the Reventazon River is one of eight that is in critical condition, according to a report by the National Laboratory of Materials and Structural Models (Lanamme).

The Chinese company, China Harbour Engineering Company (CHEC), in charge of the reconstruction of 107 kilometers of the Ruta 32 (San Jose – Limon) project will start construction work in the second half of 2018, and not in September of this year, as originally planned.

The company says the delay is due to the fact that the Costa Rican State has not yet completed all of the necessary procedures to begin the project, such as permits to cut down trees are not processed, there are no proposals to relocate public services such as water, electricity and Internet cabling. Also, there are up to 1,000 expropriations of pending land and an archaeological study to be done.

All this will delay, at least a year, the start of the project.

- Advertisement -

In an article on Nacion.com, Zhou Jingxiong, project manager for (CHEC), the Chinese state-owned construction company said, “… that these problems will prevent them from starting in September, as the contract says, and in the best of cases they could do so in the second half of 2018.”

Jingxiong added that, “… we will deliver the final designs of the new 107-kilometer route on August 15. However, the little amount of progress made by the State in the tasks that are pending will postpone the execution of the project. After the CHEC submits final plans to the National Road Council (Conavi), the administration will have 45 days to review and authorize them.”

Another problem is that there is still uncertainty as to how additional work will be financed, such as new overpasses and marginal roads that were not considered in the initial design. “… The Council is not clear where the money will come from to pay for these changes. Kenneth Solano, manager of Conavi’s executing unit, told Nacion.com that CHEC offered to lobby for an extension of the loan with Eximbank, but so far nothing has been made concrete.”

The project, “a megacarretera” will be financed a US$365 million dollar credit granted by the Asian bank Eximbank, and US$100 million dollars provided by the government of Costa Rica, which was approved by the Legislative Assembly in February of 2015. Nevertheless, the Conavi did not give the order to the Chinese until December 2016 because he did not have the environmental permits.

To get the project moving, the CHEC hired and paid for a private company to obtain environmental viability.

For Jingxiong, the Costa Rican government needs to simplify the procedures and that the institutions involved collaborate to streamline the road project.

- Advertisement -

However, the Conavi contends that CHEC should start in September despite the setbacks. The idea is that the Chinese can begin working on the 32 bridges, of the first stage of the project, because several of them do not require expropriation or relocation of services.

Despite presenting this scenario, Kenneth Solano, manager of the Conavi executing unit, did not guarantee that the work will begin in September.

- Advertisement -
Paying the bills
Q Costa Rica
Q Costa Rica
Reports by QCR staff

Related Articles

Chinese company building Ruta 32 had never suffered a bureaucratic hell like the one in Costa Rica

QCOSTARICA -- The China Harbor Engineering Company (CHEC) has successfully built...

$100 Million dollars would solve the problems on the Limón highway, says MOPT

Q COSTA RICA - Authorities of the Ministerio de Obras Públicas...

Subscribe to our stories

To be updated with all the latest news, offers and special announcements.

Discover more from Q COSTA RICA

Subscribe now to keep reading and get access to the full archive.

Continue reading