Failure In Panama Cause of Blackout in Costa Rica!

Costa Rica and some parts of Nicaragua were in total power failure for hours Saturday afternoon

Paying the bills

Latest

Can Microdose Mushrooms Boost Productivity? Find Out What Experts Are Saying

Microdosing involves taking a small, controlled amount—usually around 1/8...

“Respect for the division of powers” legislator tells President Chaves

QCOSTARICA - A call for respect for the division...

Carlos Alvarado: Populism is thriving in Costa Rica

QCOSTARICA -- On Wednesday, former president Carlos Alvarado (2018-2022),...

1960s Costa Rica

QCOSTARICA - The first indigenous peoples of Costa Rica...

Holidays left in 2024

QCOSTARICA -- Costa Rica just came off a long...

Costa Rica will not receive African migrants

QCOSTARICA -- Costa Rica's President, Rodrigo Chaves, stated on...

Dollar Exchange

¢497.92 BUY

¢504.11 SELL

18 April 2024 - At The Banks - Source: BCCR

Paying the bills

Share

For many businesses all there was to do is shut the doors until power was restored.

Q COSTA RICA – A failure in a high-voltage power transmission line in Panama produced an imbalance in the interconnect system of the Central American countries, generating a nationwide blackout in Costa Rica and some parts of Nicaragua, according to the President of the Instituto Costarricense de Electricidad (ICE), Carlos Obregon.

The Central American countries are interconnected by a 1,820 km network which extends from Panama to Guatemala. If any problems occur in the network, each country has a defense mechanism that regulates the flow of electricity.

Without power to operate traffic lights, traffic was worse than normal this Saturday afternoon

However, in today’s case, the event was of such a magnitude that the protections in the Costa Rican system could not neutralize it, causing a shut down of the electrical grid.

- Advertisement -

“When a very serious situation arises, it is practically impossible to be able to balance supply and demand, and there is a chain effect that generates the shutdown of the systems,” Obregón explained.

The blackout was reported at 1:15 pm, when all the electrical generating plants in the country shut down.

The blackout affected temporarily the operations of the San Jose airport. All passengers could do was wait it out until power was restored. (Stephanie Brenes)

Shortly after 2:00 pm, the Centro Nacional de Control de Energía (Cence) – National Energy Control Center – reported the Reventazon and Arenal plants, the largest in the country, started to come back online.

Gradually, the other generating plants also resumed operation and electrical service began to be restored gradually in all areas of the country.

Many didn’t realize until much later that the country was in the midst of a complete blackout.

President Luis Guillermo Solis, in a statement to the press at 4:00 pm, assured that power would be restored to all areas by 6:00 pm.

For the most part life in San Jose went on as normal during the blackout.

What was your experience during the blackout? Use the comments section below or post our official Facebook page your story.

- Advertisement -
Paying the bills
Rico
Ricohttp://www.theqmedia.com
"Rico" is the crazy mind behind the Q media websites, a series of online magazines where everything is Q! In these times of new normal, stay at home. Stay safe. Stay healthy.

Related Articles

Gioconda Belli: Ortega and Murillo’s Farce at the Hague

Q24N (Confidencial) Doubts assailed me as I sat down to write...

Panama expects 2.9 million tourists in 2024

Q24N -- Panama expects to receive some 2.9 million visitors in...

Subscribe to our stories

To be updated with all the latest news, offers and special announcements.

Discover more from Q COSTA RICA

Subscribe now to keep reading and get access to the full archive.

Continue reading