Reality or Pipe Dream? President Solis Promises “Platina” Bridge Fixed In One Year

Paying the bills

Latest

Can Microdose Mushrooms Boost Productivity? Find Out What Experts Are Saying

Microdosing involves taking a small, controlled amount—usually around 1/8...

“Respect for the division of powers” legislator tells President Chaves

QCOSTARICA - A call for respect for the division...

Carlos Alvarado: Populism is thriving in Costa Rica

QCOSTARICA -- On Wednesday, former president Carlos Alvarado (2018-2022),...

1960s Costa Rica

QCOSTARICA - The first indigenous peoples of Costa Rica...

Holidays left in 2024

QCOSTARICA -- Costa Rica just came off a long...

Costa Rica will not receive African migrants

QCOSTARICA -- Costa Rica's President, Rodrigo Chaves, stated on...

Dollar Exchange

¢499.09 BUY

¢504.07 SELL

19 April 2024 - At The Banks - Source: BCCR

Paying the bills

Share

On Thursday work restarted on the "definite" repair of the La Platina bridge. It's been 7 years, three governments since since.
On Thursday work restarted on the “definite” repair of the La Platina bridge. It’s been 7 years, and three governments since.

QCOSTARICA – After seven years of near fixes and three governments, President Luis Guillermo Solis this week promised to “definitely” repair the “La Platina”, the bridge of the autopista General Cañas over the Virilla river and within the next 12 – TWELVE – months.

A reality or a pipe dream? The President seems to think the former.

“We’ll finish it in one year, Minister (referring to Minister of Transport Carlos Villata) you have the responsibility to comply with my word given to Costa Ricans,” Solis said.

- Advertisement -

On Thursday, with full media coverage, President Solis took in first hand the start of the finish of this major project that has so far cost millions of dollars, the life of one worker and continues to be a headache for the some 90,000 drivers who cross the bridge every day.

All our stories on La Platina #platina

Since the 10cm (4 inch) gap on the deck of the Alajuela bound lane was noticed in August 2009, two major repair attempts (an a few small touch ups) were made. ALL FAILED.

The work this time includes expanding the bridge to six lanes (three in each direction) and pedestrian sidewalks, with the ¢7.5 billion colones (US$14 million dollars) in funding coming from the Banco Centroamericano de Integración Económica (BCIE).

President Solis said he will personally monitor the work closely, described an important, but not the “flagship project” of his administration.

- Advertisement -

The announcement for the bridge’s expansion was made last October.

Photos from the President’s Facebook page.

12742438_1234910823205101_8393070788187695937_n 11039795_1234910759871774_7068607511894496902_n 12794408_1234910749871775_9090029291530517980_n 12718232_1234910643205119_148789475711502112_n 1382805_1234910566538460_3935309190434012211_n 10422194_1234910636538453_1912327066445031175_n 12744605_1234910563205127_5634022212309064713_n 12742122_1234910569871793_2361679523088977026_n 10400825_1234910756538441_2551872120022204099_n 12734164_1234910639871786_2542075481971782837_n

- Advertisement -
Paying the bills
Rico
Ricohttp://www.theqmedia.com
"Rico" is the crazy mind behind the Q media websites, a series of online magazines where everything is Q! In these times of new normal, stay at home. Stay safe. Stay healthy.

Related Articles

Can Microdose Mushrooms Boost Productivity? Find Out What Experts Are Saying

Microdosing involves taking a small, controlled amount—usually around 1/8 to 1/10...

“Respect for the division of powers” legislator tells President Chaves

QCOSTARICA - A call for respect for the division of powers...

Subscribe to our stories

To be updated with all the latest news, offers and special announcements.

Discover more from Q COSTA RICA

Subscribe now to keep reading and get access to the full archive.

Continue reading