Route 32 has only completed 20 meters of expropriations in 20 months

The country has made an effort to try to expedite expropriations, but there has been no comprehensive reform

Paying the bills

Latest

Can Microdose Mushrooms Boost Productivity? Find Out What Experts Are Saying

Microdosing involves taking a small, controlled amount—usually around 1/8...

“Respect for the division of powers” legislator tells President Chaves

QCOSTARICA - A call for respect for the division...

Carlos Alvarado: Populism is thriving in Costa Rica

QCOSTARICA -- On Wednesday, former president Carlos Alvarado (2018-2022),...

1960s Costa Rica

QCOSTARICA - The first indigenous peoples of Costa Rica...

Holidays left in 2024

QCOSTARICA -- Costa Rica just came off a long...

Costa Rica will not receive African migrants

QCOSTARICA -- Costa Rica's President, Rodrigo Chaves, stated on...

Dollar Exchange

¢499.09 BUY

¢504.07 SELL

19 April 2024 - At The Banks - Source: BCCR

Paying the bills

Share

The system of compulsory purchase orders of property to be removed for the construction of public works in Costa Rica is failing to meet its goals.

“The country has made an effort to try to expedite expropriations, but there has been no comprehensive reform of the model and that is necessary,” said Monica Araya, former president of the Chamber of Exporters.  Image La Republica

Twenty months into the expansion of Ruta 32, which links San José to the Caribbean, the project has only received 20 meters of expropriations, and it was because their owners endorsed voluntary possession, reports La Republica.

To put it another way, the government has been able to only secure one meter of expropriated land a month, on average. And there are still 400 lots to be released, located on a 27-kilometer route, according to information provided by the contractor of Chinese capital, China Harbour Engineering Company Limited (CHEC).

- Advertisement -

Neither the approval of two reforms, in the last four years, to expedite the expropriation procedure has allowed the State to move faster in that matter.

At this pace, it may be impossible to meet the mid-2021 delivery date for the complete work.

The project entails 107.2 kilometers of road expansion between Rio Frio (Guapiles) and Limon center.

 

- Advertisement -
Paying the bills

Related Articles

Chinese company building Ruta 32 had never suffered a bureaucratic hell like the one in Costa Rica

QCOSTARICA -- The China Harbor Engineering Company (CHEC) has successfully built...

$100 Million dollars would solve the problems on the Limón highway, says MOPT

Q COSTA RICA - Authorities of the Ministerio de Obras Públicas...

Subscribe to our stories

To be updated with all the latest news, offers and special announcements.

Discover more from Q COSTA RICA

Subscribe now to keep reading and get access to the full archive.

Continue reading