Monday 20 September 2021

Failure In Panama Cause of Blackout in Costa Rica!

Costa Rica and some parts of Nicaragua were in total power failure for hours Saturday afternoon

Paying the bills

Latest

1,308 complaints about parties and agglomerations this weekend

QCOSTARICA - Police actions to enforce health regulations do...

ELON MUSK LAYS OUT WHEN TESLA WILL START RECEIVING BITCOIN

Following the series of accusations and backlash levelled against...

Top 3 Tips for Better Online Casino Security

The gambling industry has prospered over the years and...

Today’s Vehicle Restriction September 20: Plates ending in “1 & 2” CANNOT circulate

QCOSTARICA - For today, Monday, September 20, vehicles with...

Athleta women’s brand opened its first store outside North America in Costa Rica

QCOSTARICA - Gap Inc.'s Athleta brand announced the opening...

Carlos Alvarado: Vaccine retention ‘delays global solution and increases risk of new virus variables’

QCOSTARICA - Costa Rica President Carlos Alvarado showed his...
Paying the bills

Share

For many businesses all there was to do is shut the doors until power was restored.

Q COSTA RICA – A failure in a high-voltage power transmission line in Panama produced an imbalance in the interconnect system of the Central American countries, generating a nationwide blackout in Costa Rica and some parts of Nicaragua, according to the President of the Instituto Costarricense de Electricidad (ICE), Carlos Obregon.

The Central American countries are interconnected by a 1,820 km network which extends from Panama to Guatemala. If any problems occur in the network, each country has a defense mechanism that regulates the flow of electricity.

- Advertisement -

Without power to operate traffic lights, traffic was worse than normal this Saturday afternoon

However, in today’s case, the event was of such a magnitude that the protections in the Costa Rican system could not neutralize it, causing a shut down of the electrical grid.

“When a very serious situation arises, it is practically impossible to be able to balance supply and demand, and there is a chain effect that generates the shutdown of the systems,” Obregón explained.

The blackout was reported at 1:15 pm, when all the electrical generating plants in the country shut down.

The blackout affected temporarily the operations of the San Jose airport. All passengers could do was wait it out until power was restored. (Stephanie Brenes)

Shortly after 2:00 pm, the Centro Nacional de Control de Energía (Cence) – National Energy Control Center – reported the Reventazon and Arenal plants, the largest in the country, started to come back online.

- Advertisement -

Gradually, the other generating plants also resumed operation and electrical service began to be restored gradually in all areas of the country.

Many didn’t realize until much later that the country was in the midst of a complete blackout.

President Luis Guillermo Solis, in a statement to the press at 4:00 pm, assured that power would be restored to all areas by 6:00 pm.

For the most part life in San Jose went on as normal during the blackout.

- Advertisement -

What was your experience during the blackout? Use the comments section below or post our official Facebook page your story.

- Advertisement -
Paying the bills
Ricohttp://www.theqmedia.com
"Rico" is the crazy mind behind the Q media websites, a series of online magazines where everything is Q! In these times of new normal, stay at home. Stay safe. Stay healthy.

Related Articles

More than 22,000 Nicaraguans request refuge in Costa Rica in 2021

QCOSTARICA - “I know that I am here for security reasons,...

Subscribe to our stories

To be updated with all the latest news, offers and special announcements.

Log In

Forgot password?

Forgot password?

Enter your account data and we will send you a link to reset your password.

Your password reset link appears to be invalid or expired.

Log in

Privacy Policy

Add to Collection

No Collections

Here you'll find all collections you've created before.