Wednesday 8 February 2023

Moín Megaport Opening Postponed Until 2019

Paying the bills

Latest

Chaves on the Chinese balloon: “We hope it does not happen again”

QCOSTARICA - President, Rodrigo Chaves, reacted this Tuesday to...

Dollar exchange rose again this week

QCOSTARICA - To the relief of many, and not...

US announces more security support for Costa Rica for the fight against drugs

QCOSTARICA - The United States announced on Tuesday the...

China says Latin American countries ‘understand’ ‘spy balloon’ situation

Q REPORTS (EFE) The Chinese government affirmed that the...

These are the new reforms of the Simplified Tax Regime in Costa Rica

QCOSTARICA - On March 1, 2023, the new reforms...

El Salvador has the lowest homicide rate in all of the Americas, even below Canada?

Q24N (EFE) The President of El Salvador, Nayib Bukele,...

China apologizes to Costa Rica for balloon flyover

QCOSTARICA - You have most likely heard about the...

Dollar Exchange

¢577.12 Buy

¢586.15 Sell

8 February 2023 - At The Banks - BCCR

Paying the bills

Share

The original completion date for the project had been January 2018. In April, APM Terminals said the dealy would be a few months, now it says the project will be finished i January 2019.

The opening of the container terminal that is being built by APM Terminals in Limón will occur in February 2019, and not in January 2018, as originally planned.

Just weeks after APM Terminals announced that the work was to be delayed until mid-2018, they have now announced that the problems that arose during the construction process are even bigger, and will result in a delay of more than one year from the date initially agreed.

Last April. APM announced that damage to a group of 20 piles, damage to the breakwater and compaction problems would result in a delay of approximately three months.

- Advertisement -

However, when making the new schedule for delivery to the National Concessions Council (CNC), it was pointed out that the delay will be more than one year with respect to the first date.

Kenneth Waugh, manager of APM Terminals Costa Rica, told Nacion.com that “… the delay will cost between US$50 and US$60 million dollars, which must be borne by the concessionaire. That amount includes construction costs, losses due to the terminal not operating and fines. ‘We needed that time to rearrange the tasks, we had to make some decisions that had an impact on a work as complex as this and affected the different sequences and processes on the critical delivery path that is preventing us from meeting the established delivery date.'”

“… He also pointed out that the quality of the megaport, valued at US$1 billion dollars, can not be sacrificed, and that is why they are taking the time to complete the project.

The project is 73% complete according to APM

“We are not going to cut corners to speed delivery dates,” said the manager. He added that the new schedule guarantees the opening of the port in February 2019 and that none of the additional costs will impact future users of the work.

- Advertisement -
Paying the bills
Avatar photo
Ricohttp://www.theqmedia.com
"Rico" is the crazy mind behind the Q media websites, a series of online magazines where everything is Q! In these times of new normal, stay at home. Stay safe. Stay healthy.

Related Articles

Nine cruise ships simultaneously on the same day in Costa Rica

QCOSTARICA - The 2022-2023 cruise season in Costa Rica lived a...

Schaller and son confirmed dead after plane crash off Costa Rica

QCOSTARICA - Rainer Schaller, the founder of CEO of RSG Group,...

Subscribe to our stories

To be updated with all the latest news, offers and special announcements.