Ruta 39: The Nightmare With No End

Rico’s TICO BULL –The Ruta 39, better known as the Circunvalación is one of the main traffic arteries of San Jose. It starts at La Uruca, moves south towards Pavas on the west, then through the Hatillos, Alajuelita and Desamparados, the moving north to include Zapote and San Pedor on the east side of San Jose to end at Goicoechea. This intersection branches towards Calle Blancos to the west and Guadalupe to the east.

Conceived at the beginning to be a complete ring road that avoids entering the center of the capital by the INVU and Ministry of Public Works and Transportation (MOPT) in the 1950s, 20 years would pass without any work being carried out.

The MOPT hired a US consulting firm, whose report finally suggested that it was no longer feasible to build the road in the originally planned location. This report suggested that the ring be more distant from the central San Jose, towards less populated areas. Finally, the 4-lane road began to be built in 1979.

- Advertisement -

Even though it (the road know today) initially fulfilled its mission, it has shown over the years that, due to population growth and indiscriminate possession of vehicles, it is not enough as a route to avoid the congestion or “presas” as it is called in Costa Rica.

The north section, between La Uruca and Calle Blancos which was a part of the original plan and never carried out, is now a vital link to help reduce the congestion that is a daily occurrence.

But it has been a long process and one that may someday see an end. But don’t it expect this nightmare to end anytime soon.

In the early 2000s the MOPT purchased the land to complete the road, but it had not proceeded with the eviction. In 2013, the Laura Chinchilla Miranda administration announced that expropriations were finally going to be carried out.

- Advertisement -

The blue line is the missing section to complete the Circunvalacion or Ruta 39, the 5.4 km that is 40 years plus in the making.

In June 2014, the government of Luis Guillermo Solis received the approval from the Comptroller General (Contraloría) to the construction contract for the northern arc. The Consortium Estrella H. Solis (no relation to the president) was awarded the contract by the Consejo Nacional de Vialidad, a division of the MOPT.

Today, in June 2018, the new government of Carlos Alvarado informs us there is a 92% advance on the expropriations. In numbers, that there still are 8 of the 100 expropriations to be settled before the project can move forward.

From Presidencia.go.cr

Blamed for the delay is the law that governed expropriations at that time. The law was amended to speed up the process, but.

“We have to re-believe in our ability to do public works. This is a project that has had a considerable advance, even so, we need the collaboration of the courts to move swiftly on the expropriations,” said president Alvarado this past week after a review and field inspection of the ancillary work, roads that will eventually connect to the northern arc.

- Advertisement -

However, the prez did not give any commitment as to timing.

What we can take solace in, maybe, is that the current Minister of the MOPT, Rodolfo Mendez, was the minister of the MOPT on October 19, 1978, when construction of the Circunvalación began.

No one knows better the project that Mendez. He was there 40 years ago. He is there today.

“It fills me with satisfaction that we are about to conclude this important work (…) which will bring about a change in urban mobility in the Metropolitan Area,” said Minister Méndez.

The built portion of the Circunvalacion has a daily traffic of almost 100,000 vehicles.

In 1978, when construction began on the Circunvalacion, Costa Rica’s population was 2.217 million. The current population of Costa Rica is 4,951,032 as of Saturday, June 16, 2018, based on the latest United Nations estimates, of which 82.9% of the population is urban (4,106,600 people). In 1980, the urban population was 42.4% (1,012,137 people). Figures from Worldometers.info.

Do the math.

Forty years later we have basically the same roads, including the planned and unbuilt top end of the Circunvalacion.

- Advertisement -

FACT CHECK:
We strive for accuracy in its reports. But if you see something that doesn’t look right, send us an email. The Q reviews and updates its content regularly to ensure it’s accuracy.

Ricohttp://www.theqmedia.com
"Rico" is the crazy mind behind the Q media websites, a series of online magazines where everything is Q! In these times of new normal, stay at home. Stay safe. Stay healthy.

Related Articles

“Ciudad Gobierno” would give a new face to capital with a gigantic complex of buildings

QCOSTARICA - With a mega-complex of more than 153,000 square meters...

San Jose and Central Valley woke up this morning to closures and vehicular restrictions

QCOSTARICA - Due to the increase in covid infections in the...

MOST READ

Boeing boosts production capacity in Costa Rica

QCOSTARICA - The Cooperativa Autogestionaria de Servicios Aeroindustriales (COOPESA), the Costa Rican company that started as a manufacturer of bus bodies until 1993, and...

Costa Rica received the largest to date batch of covid-19 vaccines

QCOSTARICA - A new batch with 124,020 doses of the covid-19 vaccine landed on national soil this Tuesday night, as part of the weekly...

Will the new wave of COVID-19 infection threaten Costa Rica tourist recovery?

QCOSTARICA - Will the current wave of covid-19 infections cost Costa Rica's recovery of its already battered tourism? Will the wave of infections and scarcity...

Improvements begin at Quepos airport

QCOSTARICA - With the objective of boosting connectivity, regional tourism and the economic reactivation of the area, work started this Wednesday on the improvements...

Mexico City: Metro train bridge collapse leaves 23 dead

Q24N - An elevated section of metro track in Mexico City partially collapsed on Monday night, bringing down rubble and some train carriages onto...

Airport Police apprehend American carrying crocodile head

QCOSTARICA - Authorities from the Air Surveillance Service (SVA) - airport police - apprehended an American named Dale, who was in possession of an...

Government does not plan to announce expansion of restrictive measures

QCOSTARICA - The Government of Carlos Alvarado confirmed on Friday that it does not plan to announce the expansion of the restrictive measures that...

Chevrolet installs its first charger for electric cars at its headquarters in Ayarco

QCOSTARICA - With more than 1,600 electric cars of various brands circulating in the country and Chevrolet's new proposal for the second half of...

Ousting of El Salvador’s Top Prosecutor Imperils Rule of Law

Insightcrime.org - The decision by legislators aligned with El Salvador’s President Nayib Bukele to oust the country’s top prosecutor may spell the end of...

WANT TO STAY UP TO DATE WITH THE LATEST!

Get our daily newsletter with the latest posts directly in your mailbox. Click on the subscribe and fill out the form. It's that simple!

Log In

Forgot password?

Forgot password?

Enter your account data and we will send you a link to reset your password.

Your password reset link appears to be invalid or expired.

Log in

Privacy Policy

Add to Collection

No Collections

Here you'll find all collections you've created before.