Friday Afternoon Heavy Downpour Delays Work on Circunvalación

Paying the bills

Latest

Electricity rationing in Costa Rica will start on Monday

QCOSTARICA -- On Monday, May 13, electricity rationing announced...

How much do you pay in taxes for new vehicles? We compare 8 countries in Latin America

QNOTICIAS -- With the collaboration of the firm Deloitte,...

Nicaragua withdraws interoceanic canal project concession from Chinese businessman

Q24N -- In 2013, the repealed Law 840 granted...

Why your coffee may soon taste different

Q24N - Coffee is a daily routine for millions...

How much time should you spend sitting versus standing?

Q24N (The Conversation) People have a pretty intuitive sense...

Why is cancer called cancer?

Q24N (The Conservation) One of the earliest descriptions of...

What impact does the depreciation of the dollar have on different sectors?

QCOSTARICA (Revista Summa) Costa Rica is at the center...

Dollar Exchange

¢508.04 BUY

¢513.95 SELL

10 May 2024 - At The Banks - Source: BCCR

Paying the bills

Share

CircunvalacionOBRASHeroFullThe unexpected rain Friday afternoon over most of San José will mean a delay in the re-opening of the four lanes of the Circunvalación, scheduled for Monday.

The Consejo Nacional de Vialidad (Conavi) said last night that the re-opening will now take place at 5am Wednesday, when the first of two permanent concrete bridges will be operational.

The “heavy downpour” Friday afternoon caugh many by surprise.

- Advertisement -

Conavi engineer, Mauricio Sojo, said that the pouring of the concrete between the joints of the prefab concrete slabs had been scheduled for Friday, and allowing for three days to cure, the re-opening Monday was on schedule.

The last 15 days has been a nightmare for drivers of the Circunvalación in the area of Pavas and Hatillo.

Two weeks ago began the process of removing the two Bailey bridges on the southbound lanes to enable the erection of a permanent structure.

Once that is completed Wednesday (weather permitting), the process is repeated for the northbound lanes, meaning the nightmare continues for at least two or three more weeks.

Once complete, the 75 metre permanente concrete span, traffic between Pavas and Hatillo 8 – and the surrounding areas – should return to normal.

For now, while construction through the area continues, the 81.000 vehicles that use the Circunvalación daily have to put up with the delays and nightly closings from 10pm to 5am.

- Advertisement -
Paying the bills
Rico
Ricohttp://www.theqmedia.com
"Rico" is the crazy mind behind the Q media websites, a series of online magazines where everything is Q! In these times of new normal, stay at home. Stay safe. Stay healthy.

Related Articles

Electricity rationing in Costa Rica will start on Monday

QCOSTARICA -- On Monday, May 13, electricity rationing announced by the...

How much do you pay in taxes for new vehicles? We compare 8 countries in Latin America

QNOTICIAS -- With the collaboration of the firm Deloitte, in the...

Subscribe to our stories

To be updated with all the latest news, offers and special announcements.

Discover more from Q COSTA RICA

Subscribe now to keep reading and get access to the full archive.

Continue reading