Urban Train Service To Alajuela Centre Has To Wait, Says INCOFER Chief

Paying the bills

Latest

Yokasta Valle’s revenge: Golden opportunity for tourism and commerce

QCOSTARICA - Back in 2013, Costa Rican men's national...

PUSC became the big loser of May 1st

QCOSTARICA -- In alliance with the government, PUSC aspired...

How To Identify The Best CBD Vape Juice Vendor This Season?

The CBD product landscape is ever-expanding, therefore making it...

Hot mornings and afternoon showers typical during the transition to the rainy season

QCOSTARICA -- The weather service, the Instituto Meteorológico Nacional...

The 5 most common banking scams generated by Artificial Intelligence

Up to US$25 million were stolen in the world...

Find out who the new councilors of your canton are starting this May 1st

This May 1, mayors, councilors, and alternates elected in...

Dollar Exchange

¢504.80 BUY

¢511.40 SELL

03 May 2024 - At The Banks - Source: BCCR

Paying the bills

Share

 The repair of the railway line to get to Alajuela continue in the vicinity of San Joaquin in the canton of Flores, Heredia. In this community Incofer arriving in April, when fulfilled the first stage en route to Alajuela. | MARIO ROJAS.

The rehabilitation of the railway line to Alajuela has reached San Joaquin de Flores, Heredia, with service commening mid April. Work on the line will the ontinue to Rio Segundo in Alajuela (near the airport)  in September, then the INCOFER must wait for new funding to reach Alajuela Centre. Photo Mario Rojas, La Nacion

QCOSTARICA – The urban train service to Alajuela Centre (Centro in Spanish) is currently derailed due to lack of funds by the Instituto Costarricense de Ferrocarriles (NCOFER) – the Costa Rican railway.

The Institution depends on the approval of a bill that is currently in the Legislature – Ley 18.252, fourth in line on the legislative agenda – for their legal and financial strengthening.

Guillermo Santana, head of the INCOFER, explained that with current resources, the railway cannot reach Alajuela Centre. The current funds enable it to complete the San Joaquin de Heredia tracks by mid April and the Rio Segundo in Alajuela (near the airport) by September. For this work, the INCOFER has budgeted ¢4.5 billion colones.

- Advertisement -

Santana said that once the train reaches Rio Segundo, the institution has to wait for more funds, because the plan is to develop an electrified train service from there.

ferrocarril-Alajuela-Incofer_LNCIMA20150215_0202_1
“This is part of the planning that we have within the institution and the funds available. To reach the centre of Alajuela, we must wait; hopefully the bill will be approved,” said Santana.

Soure: Nacion.com

- Advertisement -
Paying the bills
Rico
Ricohttp://www.theqmedia.com
"Rico" is the crazy mind behind the Q media websites, a series of online magazines where everything is Q! In these times of new normal, stay at home. Stay safe. Stay healthy.

Related Articles

4 parents in the US reported possible abduction of their children to Costa Rica

QCOSTARICA -- On Monday, the United States issued its yearly report...

Costa Rica’s progress in renewable energy may be at risk

QCOSTARICA (TheWeek) For nearly a decade, Costa Rica has generated 99%...

Subscribe to our stories

To be updated with all the latest news, offers and special announcements.

Discover more from Q COSTA RICA

Subscribe now to keep reading and get access to the full archive.

Continue reading