Agreement will seek that Conavi and AyA ‘talk’ to avoid damage to newly built roads

The agreement establishes that the water and sewer utility must leave the roads in the same or better condition before their work

Paying the bills

Latest

Sale of BCR, exploitation of natural gas, Ciudad Gobierno and marina for Limón could be decided by referendum

QCOSTARICA -- Given the ideological division that Costa Rica...

Foods high in calories, sugar and fat will have to include a front label

QCOSTARICA -- For consumers to have clear information about...

San Jose Airport speeds up departures and arrivals of tourists in less than an hour

QCOSTARICA -- A series of recent changes carried out...

Shortage of available hospital beds back home strands Canadian in Costa Rica

QCOSTARICA  - Suffering a medical emergency, whether it be...

The Changes in the 6 months before death symptoms- Both Physical and Emotional

Individuals and their families embark on a dramatic journey...

What occurs once your nation operates on 99 percent renewable energy?

Q24N (The Verge) While most of the world still...

How relocating from the U.S. to Costa Rica’s ‘blue zone’ totally changed this family’s life forever

QCOSTARICA (CTV) When Kema Ward-Hopper and her then-fiance Nicholas...

Dollar Exchange

¢499.75 BUY

¢504.88 SELL

26 April 2024 - At The Banks - Source: BCCR

Paying the bills

Share

QCOSTARICA – If you’ve lived in Costa Rica for some time, or even a short time, who have seen a newly paved street or repaired road only to be torn up again by workers of the water and sewer utility.

The agreement indicates that both entities must share the details of the projects from the pre-feasibility stages. Photography: Graciela Solis

And we can bet you have seen that patch of dirt to cover up the water and sewer repair left as such, in some cases, forever.

But that may have come to an end with an agreement signed between authorities of the Consejo Nacional de Vialidad (Conavi) – National Highway Council (Conavi) and the Instituto Costarricense de Acueductos y Alcantarillados (AyA) Costa Rican Aqueducts and Sewers utility.

- Advertisement -

The intention, the two state institutions reported, is to avoid damages due to lack of coordination.

With this agreement, the protocol for the construction of road and water and sewer works will facilitate that executing units of both institutions exchange information on projects in the pre-feasibility, feasibility, construction, maintenance, and even emergency care phases.

According to the information released this Wednesday, the mechanisms that they would apply include the submission of project lists, technical information for each one, coordination to relocate drinking water or sanitation infrastructure on behalf of Conavi, and the obligation of AyA to ensure that the intervened national routes remain in the same or even better conditions than the previous state.

The initiative arose at the Guanacaste dialogue table, coordinated by the First Lady, Claudia Dobles, who took the proposal to the national level.

“Through this protocol, a coordination channel is created for AyA and Conavi to talk to each other and to make improvements in the interventions they carry out on the roads. This way we will have better use of resources and more efficient works,” assured Dobles.

For Mario Rodríguez, director of Conavi, this agreement is important because both institutions work in the same physical space, carrying out relevant infrastructure works.

- Advertisement -

“There is an emphasis on coordination on the projects that are being executed to reorganize the execution times and deadlines, and so that there is a commitment on the part of both institutions for the benefit of all users”, explained Rodríguez.

For his part, Tomás Martínez, executive president of AyA, hopes that with this protocol it will be possible to work more fluidly and have the works ready in less time.

Despite their assurances, we can only hope that they are serious about their intention.

Problems of lack of coordination can be seen everywhere, on major roads to side streets, where the AyA comes in, rightly digs up the street to make a repair, but then that is it.

- Advertisement -

Now, if only Conavi director Rodríguez could reach a similar agreement with the Instituto Costarricense de Electricidad (ICE) and its subsidiary, the Compañia Nacional de Fuerza y Luz (CFNL) to move their poles to the side of the road after a road upgrade.

 

 

- Advertisement -
Paying the bills
Rico
Ricohttp://www.theqmedia.com
"Rico" is the crazy mind behind the Q media websites, a series of online magazines where everything is Q! In these times of new normal, stay at home. Stay safe. Stay healthy.

Related Articles

AyA’s infrastructure execution rate is typically around 48.8%, leading to a water crisis in the GAM

QCOSTARICA -- The recent water supply crisis in the Greater Metropolitan...

Xylene (Xileno), the contaminant found in Costa Rica’s GAM drinking water

QCOSTARICA -- The Universidad de Costa Rica (UCR) - University of...

Subscribe to our stories

To be updated with all the latest news, offers and special announcements.

Discover more from Q COSTA RICA

Subscribe now to keep reading and get access to the full archive.

Continue reading