Way Clear For Expansion of the Santamaría (San Jose) Airport

Paying the bills

Latest

“We have not seen a drought like this in 50 years”: ICE expert

QCOSTARICA -- Costa Rica has implemented rationing as a...

First schedules of power outages for next week

QCOSTARICA -- Following are the official channels of the...

Electricity rationing in Costa Rica will start on Monday

QCOSTARICA -- On Monday, May 13, electricity rationing announced...

The Titles That Shape the Live Casino Section

Aside from the classic selection of slots and table...

How much do you pay in taxes for new vehicles? We compare 8 countries in Latin America

QNOTICIAS -- With the collaboration of the firm Deloitte,...

Nicaragua withdraws interoceanic canal project concession from Chinese businessman

Q24N -- In 2013, the repealed Law 840 granted...

Why your coffee may soon taste different

Q24N - Coffee is a daily routine for millions...

Dollar Exchange

¢508.04 BUY

¢513.95 SELL

10 May 2024 - At The Banks - Source: BCCR

Paying the bills

Share

rumano-Avianca-Juan_Santamaria_LNCIMA20150225_0102_5

QCOSTARICA – The possibility of the Juan Santamaria (San José – SJO) airport having 18 boarding gates and able to handle more than seven million passengers a year, is close to becoming reality.

Finally, the ground moving work has begun so the airport expansion to the west can occur, that includes the relocation and demolition of the Coopesa aircraft maintenance hangar, the relocation of the fire station and domestic (Sansa) terminal and the construction of new gates.

- Advertisement -

Currently, Aeris, the airport manager, is continuing with expansion work on the east side of the terminal, work that will allow multiple large aircraft simultaneously.

Alvaro Vargas, CEO of Civil Aviation (Aviación Civil), says the official approval of Aeris’ master plan is expected next month, that will pave the way in 2017 for the first phase of the project – the demolition work of the Coopesa hangar and environmental clean up of the area, followed by the relocation the fire station and domestic terminal and new construction of same.

In 2018, work will start on the second phase, that includes the construction of 1.000 square meters (11.000 square feet) for boarding gates.

Aeris says the investment of over US$20 million dollars.

Besides the benefits to users of the expanded terminal, benefits include allowing the Coopesa, from its new worshop, to work simultaneously on up to six Boeing 757 aircraft, according to Coopesa general manager, Gabriel Gonzalez.

The plan for the domestic terminal is to relocate it totally away from the international terminal and the fire station will be relocated on the south side of the airport, across from the terminal building, south of the runway, near the La Candela restaurant.

- Advertisement -
Aerial view of the San José airport
Aerial view of the San José airport

According to Aeris and Civil Aviation:

  • Construction of the new Coopesa hangar is expected to start immediately
  • In 2016, the relocation of the Sansa terminal and fire station will take place
  • In 2017, the then old Coopesa hangar will be demolished
  • In 2018, construction of the first three new boarding gates begins
  • Before 2026 (the Aeris lease expiry), the construction of the last three boarding gates

Source: Larepublica.net

- Advertisement -
Paying the bills
Rico
Ricohttp://www.theqmedia.com
"Rico" is the crazy mind behind the Q media websites, a series of online magazines where everything is Q! In these times of new normal, stay at home. Stay safe. Stay healthy.

Related Articles

“We have not seen a drought like this in 50 years”: ICE expert

QCOSTARICA -- Costa Rica has implemented rationing as a result of...

First schedules of power outages for next week

QCOSTARICA -- Following are the official channels of the eight electricity...

Subscribe to our stories

To be updated with all the latest news, offers and special announcements.

Discover more from Q COSTA RICA

Subscribe now to keep reading and get access to the full archive.

Continue reading